Telangana RERA Penalizes Sterling Homes ₹18 Lakh for Project Delays.
HYDERABAD: The Telangana Real Estate Regulatory Authority (RERA) has levied a penalty of ₹17.9 lakh on Sterling Homes Private Limited for failing to complete the “Sterling Orchids” residential project within the timeline specified under its RERA registration.
Located in Mallampet Village, Medchal-Malkajgiri district, the project was initially scheduled for completion by July 1, 2023, with a grace period extending to December 2023.
However, with significant delays, RERA has directed the developer to finish all pending work within 90 days from November 14, 2024.
The action follows a complaint filed by flat buyers Allam Nagaraju, S. Arun Kumar, and others, who alleged multiple violations, including delays in project delivery and deviations from the approved construction plan.
According to the complainants, Sterling Homes did not adhere to the sanctioned plan, particularly in constructing the clubhouse and ensuring a compound wall to separate the project from its adjacent Phase II development.
They also accused the developer of misleading buyers by sharing amenities between Phase I and II without prior disclosure. Further, they alleged that Sterling Homes relocated the Sewage Treatment Plant (STP) in violation of the approved plan and began work on Phase II before completing Phase I, thereby compromising the rights of Phase I buyers.
In response, Sterling Homes defended itself in its submission to Telangana RERA (TGRERA), citing external factors such as regulatory hurdles, heavy rainfall, labour shortages, and disruptions caused by the pandemic as reasons for the delays.
The developer maintained that the deviations from the approved plan were minor adjustments made to ensure structural integrity and had been approved by the relevant authorities.
Sterling Homes denied allegations of malafide intent, asserting that Phase II construction was initiated only after securing the necessary approvals and that buyers had been informed about the shared amenities.
It further claimed that financial constraints, exacerbated by the complainants’ alleged non-payment of dues, contributed to the delays in completing Phase I.
In its ruling, RERA ordered the developer to complete all remaining work in the Sterling Orchids Phase I project, including promised amenities, strictly in line with the sanctioned plan, within 90 days.
Additionally, RERA mandated Sterling Homes to pay interest at a rate of 10.95% per annum to the complainants for the amounts already paid, as outlined in the Agreement of Sale.
At the same time, the complainants were directed to clear any pending sale consideration amounts within 45 days to facilitate the project’s progress. Both parties have been instructed to fulfill their respective obligations to ensure the project’s timely completion and prevent further disputes.